This section describes how to order locks, which are in the In planning state, on iLOQ Manager.
You can distribute system administration by allowing one user to order, that is, approve, programming changes to locks. Another user, for example, with limited usage rights, can carry out ordered programming tasks, but cannot modify the content of these programming tasks.
If you do not use distribute system administration, you can carry out the ordered programming tasks yourself. In any case, ordering is a mandatory phase in the system.
When you order a lock, the programming task is created and sent to the iLOQ S10 Locking System server, where it waits to be transferred to the lock through the Programmer or, remotely, over a network to networked locks.
Proceed as follows.