Select your region or visit global site

Support
Open navigation

Finalizing the Bus Device Configuration on Net Bridge

This section describes how to finalize the bus device configuration on the Net Bridge.

Make sure that you have:

Proceed as follows.

  1. Switch the Net Bridge MODE switch to SETUP.
  2. Ensure that the Net Bridge  switch is ON.
  3. Wait for three seconds.
  4. Switch the Net Bridge MODE switch to OPERATING.
  5. An internal test procedure is started.

    Observe the green FUNC led for approximately one minute until the Net Bridge has saved the bus configuration. Check that:

    1. The green FUNC led blinks as many times as there are devices on the main bus.
    2. After a pause, the green FUNC led blinks as many times as there are devices on the reader buses.
    3. After a pause, the green FUNC led blinks as many times as there are lock cylinders connected on Door Modules.

    Saving the bus configuration ends when the FUNC led is constantly illuminated green.

    The procedure ends when constant green FUNC, RS-485 STATUS, SYSTEM STATUS, and SERVER CONN. leds are illuminated.

  6. Check that the Door Module POWER, DEVICE, BRIDGE and SERVER leds are illuminated green in all door modules.
    Check also that the topmost led is illuminated green on all Programming Hot-spots.
  7. Deployment may require additional configuration on S10 Manager according to the Quick Guides.

Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select atleast one of the reasons

Feedback sent

We appreciate your effort and will try to fix the article

Didn't find what you were looking for?

Submit a ticket